BAS 89282
Allermöher Pumping Station Ditch Bridge
Keine weiteren Bilder verfügbar
Germany
Hamburg
Hamburg
Main drainage ditch Allermöhe
A25 motorway
Slab girder bridge, girder bridge
prestressed concrete
1975
0.00 m
41.68 m
29.00 m
0.00 m
0.00 m
1228.00 m2
in operation
The bridge consists of two substructures:
1. 4-span superstructure with slab girder cross-section, length 41 m, width 16 m, area 679 m²
2. 3-span superstructure with slab girder cross-section, length 41 m, width 13 m, area 549 m²
BSU Amt V - Bund LSBG-B3 / Bezirk Bergedorf
709 (ASB: 2526030)
A map is loading